Job Description (Addition)
project
1e74aea1b1401e2f
Normalized: job description addition
moreland_contracts
39%
Separation Confidence
How distinct this entity is from others. Higher means no close matches existed when it was created. Lower means a near-match was rejected just below the 80% threshold — worth reviewing.
Moderate — a somewhat similar entity exists
100%
Avg Match Confidence
The average confidence score across all active source mappings. Shows overall quality of linkage between source records and this canonical entity.
Strong source linkage
Source Mappings (1)
| Source | Source ID | Display Name | Confidence | Method | Status | Actions | |
|---|---|---|---|---|---|---|---|
| moreland_contracts | 4fc02904f00116b72aa1cd336e7a23cc | Job Description (Addition) | 1.00 | fuzzy+embedding | Active |
|
|
|
Source Record
bronze_moreland_contracts_ma_project_contracts
file_hash
4fc02904f00116b72aa1cd336e7a23cc
file_name
SOW Template addition Final.docx
file_path
https://morelandpartners.sharepoint.com/sites/MorelandConnect-BusinessDevelopment/_layouts/15/Doc.aspx?sourcedoc=%7B7C08D934-C84C-40A1-B47E-158ACA7D7997%7D&file=SOW%20Template%20addition%20Final.docx&action=default&mobileredirect=true
company
Payne & Tompkins Design Renovations LLC
project_name
Job Description (Addition)
contact_person
—
contract_type
time_and_materials
hourly_rate
—
estimated_hours
—
total_fee_estimate
—
brief_project_description
Addition to existing structure including various renovations and installations.
start_date
—
extracted_at
2026-07-24T02:27:12.452853+00:00
raw_text_preview
Job Name – Job Description (Addition)
General Standard Best Practices Provided by Payne & Tompkins Design Renovations LLC
Project Preparation
Onsite walk-through with client to review site staging
Seal off rooms not being worked in
Seal off all ductwork openings to prevent any dust from migrating elsewhere in the home
Make certain dumpster is on boards to protect driveway
Install lockbox with key on homeowner approved door
Provide Portable commode
Project Close-out
Conduct final walk-through with Owner
Test all outlets, confirm hot cold faucet orientation as needed
Remove any packing materials, protective coatings on any finish items
Clean entire work area with professional cleaning company
Clean all windows, glass doors, shower doors, or mirrors
Broom clean and mop unfinished areas
Remove Portable commode
Remove Dumpster
Exterior Scope of Work
Note: Can be split by project or by full exterior scope.
Example: multiple additions, split work in different areas, etc.
Specific work area starting and ending points (use pictures to clarify):
Start: ______________
Stop:______________
Work outside of this area will be defined and priced on a change order
Utilities
Electrical
Disconnect existing meter and prep for relocation.
Supply and installation of new temp pole.
Purchase and install feed wire in PVC conduit from street to new meter
350’ allowance
Purchase and install (1) new 400-amp meter main
All phone and cable hookups to be removed by owners’ utility company.
Storm water waste
Supply and install new 4” SDR35 to new downspout locations
Tie into existing downspout locations or daylight onsite per site plan
No culvert work, catch basins, or other hidden storm water mitigation included unless listed above
Sanitary waste
Perform new septic tie-in once foundation is built.
Domestic water supply
When drilling a new well, please be aware that the scope of work does not cover rock drilling. If rock is encountered during the well drilling process, you will b